  1. Sandy Disaster Relief Appropriations Act, 2013 -2 and Division B: Sandy Recovery Improvement Act of 2013.  
  2. The American Recovery and Reinvestment Act (ARRA) 

Does a contract under a federal grant have to follow the Davis-Bacon Act? 

The Davis-Bacon Act is not applicable to any passthrough funds (subawards or contracts) if the initial federal award is exempt for Davis-Bacon requirements. However, if a State has a prevailing wage law in place, there may be a requirement depending on that State’s legislation.

...